Future Developments at Fleetwood Health and Fitness Centre

We are thrilled to announce the start of major refurbishment works at Fleetwood Health and Fitness Centre!
We are investing heavily to upgrade our facilities and bring you a fresh, modern experience. To keep as much of the Centre open for you as possible and reduce disruption, the project is being delivered in stages. To minimise disruption, work is taking place across three planned phases starting September 2026.
 

What changes are being made? 

Main Reception: 

  • Replacement of the primary entry door and wall into the sports hall as well as the rear door behind the reception desk.
  • Full refurbishment of the existing desk, including a new counter surface and refreshed exterior finishes.
  • Small power modifications, replacement of all flooring, and complete redecoration of walls across the main reception area and connected circulation paths.

Wet Changing Rooms: 

  • Upgrading flooring & walls: Installing new non-slip tiled floors with full waterproofing, alongside fresh hygienic wall panelling.
  • Modernising changing cubicles & lockers: Adding 42 brand-new changing cubicles and fully refurbishing the lockers.
  • Adding a new vanity area: Complete with hairdryers, mirrors, feature lighting, seating, and bag storage.
  • Updating toilets & shower facilities: Replacing all sanitaryware, fitting new toilet cubicles, upgrading accessible facilities, and servicing existing showers.
  • Refreshing fixtures & lighting: Fitting new internal doors, energy-efficient lighting, and brand-new washroom accessories... plus more!

Sports Hall and Gym: 

  • We’ve placed orders with fitness equipment providers Life Fitness and Physical Company to replace ALL of the equipment in the gym. There will be a comprehensive mix of cardio machines, fixed resistance machines, free weights and functional training equipment. Particular highlights will include cardio machines with16 inch “SE4” touch screens with full internet connectivity and a wide range of immersive on-demand workouts. An extensive range of cable resistance equipment including an 8 stack multi-jungle with various row & pulldown attachments. Two squat rack with integrated deadlifting platform & bumper plates and much, much more. There will also be a very large, dedicated functional training zone with sled track, Assault bike, Ski Erg and Rowing Machines. Installation of new feature hex lighting, full small power upgrade, new emergency lighting, replacement of wall-mounted extract fans, and modifications to the fitness speaker system.
  • Full-height wall redecoration and installation of brand new flooring throughout using purpose made 40mm rubber tiles.
     

Can I still use the Centre? 

Yes, while some areas of the Centre will be closed during the works, the rest of the Centre will remain open. Please note the following closure dates and alternative entry points:

10 September – 20 September: Main Reception and the pool hall corridor will be closed. The Gym can be accessed via the fire exit on the side of the building. The Pool can be accessed via the Splash Pad entrance and up the ramp. Please follow directional signage on-site.
21 September – 3 October: The Sports Hall & Gym will close for two weeks for painting, electrical upgrades, and preparation for the gym upgrades, which are expected to begin the week commencing 30 November. Please note that during this stage, entrance to the building will be back to normal.
21 September – 13 November: Changing Rooms will close for 8 weeks for a complete overhaul. Swimmers must arrive swim-ready while the changing rooms are closed, and there will be limited poolside showers available.

During the closures, members are encouraged to make use of the recently refurbished facilities at Poulton Health and Fitness Centre and Thornton Health and Fitness Centre.
 

What are the proposed dates? 

Work officially commences on 14 September 2026.

  • Phase 1 (Reception Closure): 10 September – 20 September
  • Phase 2, Part 1 (Sports Hall & Gym prep): 21 September – 2 October and reopening on 3 October.
  • Phase 2, Part 2 (Wet Changing Rooms): 21 September – 13 November
  • Phase 3 (New Gym Installation): Expected to begin W/C 30 November. 
     

What will happen to Group Exercise Classes?

Group exercise classes will continue as normal throughout the project.
 

How will I know what's going on?

We will be in touch throughout the work so keep an eye on your inbox! We will also be posting regular updates on our social media pages and website. 
 

Can I use other facilities?

Members wanting to use alternative facilities can visit the ‘sister’ sites at Poulton Health and Fitness Centre and Thornton Health and Fitness Centre.
  

What will happen to my membership?

There will be no changes to your existing membership. All memberships will be unaffected by this project and payments will continue as per normal.
 

What if I have more questions?

Please speak to a member of our team in the Centre or use the contact us page on our website.